Over the holidays, the last few science fixes went into the system, and the spinup periods resumed. Each of the three MERRA processing streams is presently running, with the data to be discarded for spinup.

  • Stream 1 RUNNING at 08/31/78
  • Stream 2 RUNNING at 07/30/88
  • Stream 3 RUNNING at 07/30/97
As a reminder, the planned start day for each stream is Jan 1, 1979, 1989 and 1998 respectively. They are moving at approximately 10 days per day, when the computer systems are up. They will hold at the end of each November, so that the last patch of the system (engineering fixes to the output diags, scripting and post processing that do not affect science) can be put into place. At that time, the GMAO will also make an evaluation of the output diagnostics, to ensure that the data and units all match the file spec document.

There is a known issue already becoming apparent. The CRTM coefficients for NOAA 8 AMSUA channel 14 have some problems. This data doesn't begin until May 1983, so there is time to correct the problem without affecting the MERRA production schedule. Further updates as the run get closer will be provided.

Happy New Year!